Realize Construction.

Delivering Gigascale.

The Tesla Gigafactory in Grünheide has established a highly integrated production site for electric vehicles. The campus combines vehicle production, battery manufacturing and central infrastructure, and is designed for industrial scalability, high production rates and efficient mass production.

#Industrial Construction, #Construction

3
million m² total area
500
thousands of metric tons of concrete
729
thousands of square meters of built-up area
3000
km of cable
Project Coordination
Supplier Management
Contract & Claim Management
Cost Control

»ahc delivers. Strong presence, swift decision-making, clear escalation procedures and consistent implementation – exactly the combination you need when deadlines and quality must both be met. — Dennis Döring.«

Dennis Döring, Staff Construction Manager Tesla

With the Gigafactory Berlin-Brandenburg, Tesla has established a highly integrated production site in Grünheide for the mass production of electric vehicles. On a site covering approximately 3.0 million m², a comprehensive industrial system has been created that closely integrates production, logistics and infrastructure, and is designed for speed, scalability and efficiency.

ahc GmbH took on project management, quantity surveying and construction management tasks, managing costs, contracts and construction processes in a highly dynamic and concurrent environment. We coordinated the project stakeholders, created transparency in cost development and ensured the structured execution of construction works.

A key focus was on contractual management and handling changes within a highly dynamic project environment. Through the close integration of cost control, supplier management and claims management, impacts were identified at an early stage and a robust basis for decision-making was established.

The particular challenge lay in the simultaneous implementation of construction, commissioning and production processes, as well as in the high technical complexity of the site. The factory was to be understood not as a traditional construction project, but as an integrated production system with closely coordinated processes and complex interfaces.

Let’s work together.

Big projects need strong partners. We’re ready. Get in touch and let’s have an informal conversation about your challenges.

Request a callback

    Contact person

    Alexander Scholz

    Vice President Operations and Head of Sales
    alexander.scholz@ahc-gmbh.de